The challenge
During the FIFA Women's World Cup, last-minute decorating works were needed across corporate areas of the stadium — on a tight deadline, in a live venue, without compromising quality.
Our approach
Our protective coatings team carried out abrasive blasting to steel stubs located within confined and limited-access areas, followed by protective coating systems. Careful planning and specialised techniques were needed to safely access and prepare these areas, with coatings applied in accordance with specification for long-term durability.
The result
Critical painting works completed on time for the tournament. JMA continues as a contractor to the Trust across general decorating and technical structural coatings.
“Not only were JMA responsive to our needs but also demonstrated the remarkable quality of completing the critical painting works without compromising on quality.”
Terry Clubb — General Manager Facilities, Sky Stadium